PUBLISHED ON March 20th, 2019

Construction of Nairobi-Naivasha SGR 90pc complete

Construction of the 120km Nairobi-Naivasha standard gauge railway (SGR) is 90 percent complete, 16 months after work on the project started.

Kenya Railways acting managing director Philip Mainga expressed optimism that the rail will be completed ahead of the June deadline, despite a compensation stalemate along Rongai and Ngong sections.

“Phase 2A of the Nairobi-Naivasha SGR line is 90 per cent done and we are still on course to finish the project by May 31,” said Mr Mainga.